SCHEDULE:

 

Out for Bids

March 18, 2024

Mandatory Pre-bid Meeting

Custer II Elementary, April 1, 2024 @ 9:00am

Raisinville Elementary, April 1, 2024 @ 10:00am

Arborwood South Elementary, April 1, 2024 @ 11:00am

Official Bidders List

April 2, 2024

Bids Due

April 16, 2024 @ 3:00pm

Post Bid Interviews

April 16-17, 2024

Architect Recommendation

April 18, 2024

Owner Awards Project

April 23, 2024

Notice to Proceed Letters

April 24, 2024

Pre-Construction Meeting

TBD

Physical Construction

June 10, 2024 – August 16, 2024

Substantial Completion

August 16, 2024

Final Completion

September 16, 2024