SCHEDULE:

Out for Bids                                           July 12, 2022

Mandatory Pre-bid Meeting                  July 27, 2022

Official Bidders List                               July 28, 2022

Bids Due                                               August 10, 2022

Post Bid Interviews                               August 11-12, 2022

Architect Recommendation                  August 12, 2022

Owner Awards Project                          August 23, 2022

Notice to Proceed Letters                     August 24, 2022

Pre-Construction Meeting                     T.B.D.

Physical Construction (Boiler Rm.)       May 12, 2023

Physical Construction (All Other)          June 19, 2023 – August 18, 2023

Substantial Completion                         August 18, 2023

Final Completion                                   September 18, 2023