SCHEDULE:
Out for Bids July 12, 2022
Mandatory Pre-bid Meeting July 27, 2022
Official Bidders List July 28, 2022
Bids Due August 10, 2022
Post Bid Interviews August 11-12, 2022
Architect Recommendation August 12, 2022
Owner Awards Project August 23, 2022
Notice to Proceed Letters August 24, 2022
Pre-Construction Meeting T.B.D.
Physical Construction (Boiler Rm.) May 12, 2023
Physical Construction (All Other) June 19, 2023 – August 18, 2023
Substantial Completion August 18, 2023
Final Completion September 18, 2023